Scheduled for November 22, 2024 at 2:00 AM – 5:00 AM
Affects
DET01 (Detroit, MI)
Updates
Completed
November 22, 2024 at 5:00 AM
Completed
November 22, 2024 at 5:00 AM
Maintenance has completed successfully
Update
November 22, 2024 at 3:56 AM
In progress
November 22, 2024 at 3:56 AM
Extended maintenance period for 1 hour. Still working through this.
Update
November 22, 2024 at 3:06 AM
In progress
November 22, 2024 at 3:06 AM
Beginning our network maintenance.
Update
November 22, 2024 at 2:22 AM
In progress
November 22, 2024 at 2:22 AM
EPYCK01.DET01 hardware upgrade has been completed. VMs are coming back online.
We will be taking a short break to prepare for the network upgrade.
Update
November 22, 2024 at 2:03 AM
In progress
November 22, 2024 at 2:03 AM
Working on this now. EPYCK01.DET01 is coming offline for a hardware upgrade.
In progress
November 22, 2024 at 2:00 AM
In progress
November 22, 2024 at 2:00 AM
Maintenance is now in progress
Planned
November 22, 2024 at 2:00 AM
Planned
November 22, 2024 at 2:00 AM
During this maintenance window, we will be performing network maintenance on our core router, installing a redundant 10G network drop to add some redundancy and improve overall network health.
We will also be performing scheduled maintenance on EPYCK01.DET01 to upgrade its hardware. The hostnode will be powered off, meaning your instance will also be offline for a period of time of up to 20 minutes while we perform the upgrade.
This maintenance is scheduled for Thursday, November 21st 2024 between 9PM and 11PM EST.